HEATER ASSEMBLY > INSTALLATION |
for Preparation Click here
1. INSTALL WATER PIPE AND HOSE SUB-ASSEMBLY |
Install the water pipe and hose with the nut and bolt.
- Torque:
- 9.8 N*m{ 100 kgf*cm , 7 ft.*lbf }
Connect the heater hoses.
2. INSTALL HEATER PUMP ASSEMBLY |
Install the heater pump with the nut.
- Torque:
- 9.8 N*m{ 100 kgf*cm , 7 ft.*lbf }
Connect the fuel hoses.
3. INSTALL POWER HEATER ASSEMBLY |
Install the heater with the 2 bolts and 2 nuts.
- Torque:
- 9.8 N*m{ 100 kgf*cm , 7 ft.*lbf }
Connect the fuel hose.
Connect the heater hoses.
Connect the connectors.
4. INSTALL EXHAUST PIPE SUB-ASSEMBLY |
Install the exhaust pipe with the 2 nuts and bolt.
- Torque:
- 9.8 N*m{ 100 kgf*cm , 7 ft.*lbf }
5. ADD ENGINE COOLANT |
For 2AD-FHV: (Click here).
6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
7. CHECK SRS WARNING LIGHT |
Check the SRS warning light (Click here).
8. WARM UP ENGINE |
9. CHECK HEATER SYSTEM |
After the heater switch is turned ON and 20 seconds have passed, touch the part of the fuel hose labeled A in the illustration and check that the hose is vibrating.